Future Fuels Challenge 2026–27: Frequently Asked Questions
About the Challenge
The Future Fuels Challenge is the Fuel Innovation Fund’s annual competitive funding call for projects that reduce greenhouse gas (GHG) emissions and the lifecycle carbon intensity (CI) of transportation fuels in Canada. The second iteration of the Challenge makes up to $50 million available, with $1 million to $10 million per project, for projects that pilot, demonstrate, or deploy clean fuel technologies at first-of-kind commercial scale.
The Fuel Innovation Fund is a federally registered Emission Reduction Funding Program under Canada’s Clean Fuel Regulations (CFR). It is a subsidiary of Emissions Reduction Alberta (ERA), which administers it. The Fund reinvests compliance contributions into projects that reduce emissions, support economic development and improve environmental outcomes in the transportation fuels sector.
Funding comes from primary fuel suppliers regulated under the Clean Fuel Regulations. The CFR sets increasingly strict annual targets for reducing the carbon intensity of fuels. Contributing to a registered fund such as the Fuel Innovation Fund is one way these suppliers can comply, covering up to 10 per cent of their annual reduction obligations. The Fund reinvests those contributions into Canadian projects.
Many promising clean fuel technologies are near-commercial but not yet widely deployed. The Future Fuels Challenge helps move them into real-world operation by supporting high-readiness projects that can deliver verifiable emissions reductions within five years. Interest in the inaugural Challenge far exceeded available funding: more than 100 applications were received, and $48.1 million was awarded to eight projects representing more than $388 million in total investment.
The Fuel Innovation Fund offers two Canada-wide funding streams:
- Contributor Reinvestment Program: accepts proposals on a continuous basis from regulated contributors to the Fund.
- Future Fuels Challenge: an annual competitive call open to a broad range of applicants, whether or not they are regulated under the CFR.
Eligibility and Scope
The Challenge is open to all categories of lead applicant, whether they contribute to the Fund or are regulated under the CFR. Example applicants include:
- innovators and technology developers
- fuel producers and suppliers
- Indigenous communities
- industrial facility owners and operators
- industry associations
- small and medium-sized enterprises
- research and development organizations and universities
- municipalities
- not-for-profit organizations
- consortia of multiple partners
Collaboration is encouraged, including partnerships with post-secondary and research institutions, Indigenous communities and municipalities.
For the Future Fuels Challenge, the transportation sector includes road, rail, marine and aviation.
The Challenge is not technology prescriptive. Any technology may be proposed if it supports the Challenge’s objectives and delivers measurable reductions in GHG emissions or the lifecycle CI of transportation fuels in Canada. Projects don’t need to be eligible for CFR credit generation.
Example technologies include:
- energy efficiency upgrades, advanced process control, digital optimization, and heat integration or recovery at fuels-sector facilities
- novel processes and chemistries for refining and fuel production
- fuel switching and electrification, including thermal energy storage
- on-site clean electricity and heat production, such as wind, solar or geothermal, at fuels facilities
- carbon capture and storage for fuel production facilities
- methane emissions reduction, including from flaring, venting and purging in upstream oil and gas operations
- co-processing of biogenic feedstocks in refineries
- production of biofuels from biomass or waste feedstocks, such as renewable diesel, biodiesel, hydrotreated vegetable oil (HVO) and biocrude upgrading
- production of low-CI ethanol and advanced bio-ethanol
- production of sustainable aviation fuel (SAF)
- renewable natural gas and biofuels from organic waste, landfill gas, and agricultural or forestry residues
- production of synthetic fuels and e-fuels
- low-emissions hydrogen production, and hydrogen fueling, storage and transportation
- electric vehicle charging infrastructure, including grid integration
The Challenge targets high-readiness projects that will reach Technology Readiness Level (TRL) 7 to 9 by project completion:
- Field test or pilot (about TRL 7): scaling up a prototype to representative pilot size and testing it in an operational environment.
- Demonstration (about TRL 7 to 8): operating a near- or full-commercial-scale system in an operational environment.
- First-of-kind implementation (about TRL 9): designing, building and operating the technology in its final commercial form and at commercial scale. This can include a novel implementation for a region, application or segment of the transportation sector.
Technologies may be below TRL 7 when the project starts. Applicants must explain how the project will reach the target stage and must demonstrate that the project will achieve measurable emissions reductions.
Yes. Regardless of TRL, projects are only eligible if they achieve GHG reductions within the project scope, and those reductions must begin by June 30, 2031. For example:
- A pilot plant producing clean fuel for sale in Canada could be eligible.
- A project limited to feedstock processing, or to small-batch fuel production for certification, would not be.
Projects that switch to clean fuels can include both supply (fueling or charging infrastructure) and demand (vehicles), such as a heavy-duty zero-emission vehicle pilot with charging. Applicants must demonstrate how the vehicle investment is part of a novel approach that helps develop the broader clean fuels ecosystem. Projects focused mainly on routine purchases of commercially available zero-emission vehicles, such as light-duty fleet conversions, are not eligible.
Pre-construction work, such as front-end engineering design (FEED), is eligible only as part of a project with a direct line of sight to emissions reductions within five years. Standalone studies are not eligible.
Projects must be demonstrated or implemented in Canada and show a clear value proposition for reducing GHG emissions in Canada. Technologies and project partners, such as technology vendors, can come from anywhere in the world. Projects across multiple Canadian sites are eligible.
EOIs that fall into any of these categories will be screened out:
- projects that don’t deliver direct, measurable GHG or CI reductions in the fuels value chain by 2031, including projects that only indirectly enable reductions (such as critical minerals projects)
- projects without sufficient relevance to Canada’s liquid fuels supply chain or transportation sector
- routine purchases of commercially available zero-emission vehicles
- business-as-usual projects, where Fund investment would not materially change the outcome
- standalone studies, or projects that don’t involve technology deployment or process improvement
- projects limited to feedstock processing without integration into clean fuel production
- pilots limited to small-batch production for testing or certification (for example, ASTM testing)
- projects with insufficient Canadian activity or sites
- projects with insufficient GHG benefit, or high risk and low readiness that threaten reductions within five years
- projects with a risk of significant environmental, economic or social harm
- submissions that don’t meet minimum submission standards
Yes. There is no limit on the number of proposals per applicant, but applicants are encouraged to submit only their strongest projects.
Yes. Smaller projects can be bundled to meet the $1 million minimum, provided shared project management and reporting can be justified. Examples include deploying one technology at several locations, or several complementary technologies at one location.
Funding and Terms
Up to $50 million, subject to the Fund’s discretion and the availability of funds.
Between $1 million and $10 million. Higher amounts may be considered as exceptions, with compelling justification. Applicants must justify the amount they request, and the Fund may award less than requested.
Fund contributions must be matched at least 1:1 by the applicant or private partners, so the Fund will cover no more than 50 per cent of eligible expenses. The Fund will not match other government funding provided directly to the project, although these sources can form part of the overall funding stack.
| Eligible costs | Other contributions | Maximum Fund contribution | Limiting factor |
| $8 million | $4 million from applicant and private partners | $4 million | 50% of eligible expenses |
| $50 million | $40 million from applicant, partners and/or government | $10 million | $10 million maximum |
| $20 million | $5 million private, plus $10 million government | $5 million | 1:1 private match |
Yes. There is no formal Fund stacking limit, but applicants must comply with any limits set by other programs, including the Government of Canada’s 75 per cent stacking maximum. Fuel Innovation Fund dollars are not considered Government of Canada funds. Funding from other ERA or Fuel Innovation Fund programs cannot be combined with Future Fuels Challenge funding on the same project scope.
No. The Fund will not match future revenue such as:
- TIER performance credits or CFR compliance credits
- tax incentives such as SR&ED credits
- sales of project outputs
These revenue sources don’t disqualify a project, can strengthen its financing plan, and can still be pursued.
Both capital and operating costs can be eligible. Eligible expenses can be incurred only after the Full Project Proposal (FPP) submission deadline. Earlier costs are not eligible for matching. Applicants should include all project costs, eligible and ineligible, in their proposal. Details are in the Eligible Expenses and Cost Guidelines 2027.
- Start date: Successful applicants must begin work within 120 days of funding approval. They may request a delay of up to 12 months to align with facility operations, turnarounds or regulatory processes; the Fund decides whether to accept such requests.
- First reductions: Projects must begin delivering realized GHG reductions by June 30, 2031.
- Priority: Projects that can start quickly and be partly or fully operational within three years of approval will be given priority.
The Contribution Agreement is the funding contract between the Fuel Innovation Fund and each successful applicant. It sets out:
- funding terms and the maximum Fund contribution
- project scope and work plan
- milestones, deliverables and performance targets
- payment schedule
- reporting requirements
Agreements must be signed within 60 business days of the approval notice. The Fund will consider only minor changes to its standard terms.
Funding is paid as milestones are completed, after eligible expenses have been incurred. Each payment matches the Fund’s overall share of the project. For example, if the Fund covers 25 per cent of eligible costs, it pays 25 per cent of eligible expenses at each milestone. No payments are made before the Contribution Agreement is signed.
Funding recipients must report on:
- GHG reductions, both actual and projected
- project outcomes and lessons learned
- job creation and other environmental, economic and social benefits
Under the Clean Fuel Regulations, every project must report its CO₂e reductions, when they were or will be achieved, and the method used to calculate them, with supporting evidence. Recipients may also be asked to host workshops or take part in other knowledge-sharing activities.
Intellectual property terms are set in each Contribution Agreement. In general:
- Background IP and third-party technology stay with their original owners.
- The Fund retains rights to project results, such as data and reports.
- New project technology is owned by the applicant and partners, who are expected to commercialize it, or make it available on reasonable commercial terms, for the benefit of Canada.
Only with your permission. During submission, applicants can choose to let the Fund share their proposal with ERA’s trusted funding partners that have a non-disclosure agreement in place, to explore additional funding. This choice does not affect how a proposal is evaluated.
The Fuel Innovation Fund follows ERA’s Privacy, Data Security and Confidentiality Policy and Alberta’s Records Management Regulation. The full policy is at eralberta.ca/privacy.
Submission and Timeline
Expressions of Interest (EOIs) are due January 20, 2027, at 5:00 p.m. Alberta Time (ABT, UTC-6). Late or incomplete submissions will not be accepted.
| Stage | Milestone | Timing |
| EOI | EOI submission deadline | January 20, 2027, 5:00 p.m. ABT |
| EOI | Shortlist notification and FPP invitation | Mid-March 2027 |
| FPP | FPP submission deadline | April 22, 2027 |
| FPP | Oral presentations | May 25–28, 2027 |
| FPP | Funding decisions | July 2027 |
| Execution | Contribution Agreement signed | Within 60 business days of approval |
| Execution | Project start | Within 120 days of approval |
| Execution | GHG reductions begin | By June 30, 2031 |
Submit an EOI through Grant Manager, ERA’s online application system, at grant-manager.com/erims. You will need to create an account and complete all mandatory forms. You’ll receive an automatic confirmation email; if it doesn’t arrive, check your spam folder and Grant Manager, then contact IMS@fuelinnovationfund.ca.
- Expression of Interest document (required): this forms the basis of the evaluation and must address every criterion.
- Milestone Summary Table (required)
- Readiness Checklist (required)
- Letters of support (optional): combined into a single PDF.
EOIs must use the templates provided in Grant Manager. Requirements:
- Page limit: no more than 10 letter-sized pages, including text, graphics and tables. The milestone table, readiness checklist and letters of support don’t count toward the limit, and any extra pages will be removed.
- Formatting: Calibri or Arial 11-point font, at least 1.0 line spacing and 1-inch margins.
- File names: 30 characters or fewer, including the Grant Manager proposal number.
| Question | Contact |
| Guidelines and templates | applications@fuelinnovationfund.ca |
| Grant Manager and submission | IMS@fuelinnovationfund.ca |
| GHG quantification | GHG@fuelinnovationfund.ca |
| Budgets, appendices and eligible expenses | applications@fuelinnovationfund.ca (subject: Attention Finance) |
| General inquiries | info@fuelinnovationfund.ca |
Allow up to one week for a response. The Fund does not pre-review EOIs. Shortlisted applicants may be assigned a proposal advisor and may receive support from the Fund’s GHG team.
No. During an active evaluation, applicants may contact only:
- their assigned proposal advisor
- the Fund’s Applications, GHG and Finance teams
Contacting anyone else about an active proposal is prohibited. This includes the Project Evaluation Committee, ERA or Fund executives, the Governing Committee, and government officials. Such contact may be reported to the Fairness Monitor and could disqualify the proposal. Normal stakeholder engagement on your project is still permitted, as long as it doesn’t concern the evaluation.
Evaluation
The Challenge uses a two-stage, competitive and merit-based process overseen by an independent Fairness Monitor:
- EOI stage: eligibility screening, then merit evaluation of eligible EOIs.
- FPP stage: shortlisted applicants submit a full proposal and give an oral presentation to the Project Evaluation Committee, a panel of independent technical, environmental and financial experts.
The committee makes funding recommendations, and the Fuel Innovation Fund Governing Committee makes the final decisions.
| Criterion | Weight |
| Technology strength | 20 |
| Business case and market | 20 |
| Readiness and implementation | 35 |
| GHG, environmental, and economic benefits | 25 |
| Total | 100 |
Projects that don’t show adequate readiness, or verifiable GHG reductions within five years, will not be shortlisted.
| Category | Criterion | Weight |
| Impact (40) | Strategic alignment | 5 |
| Market potential | 5 | |
| GHG benefits | 15 | |
| Environmental benefits | 5 | |
| Economic benefits | 10 | |
| Deliverability (60) | Technology strength | 15 |
| Economic viability | 10 | |
| Implementation plan | 15 | |
| Readiness and financing | 15 | |
| Team and partnerships | 5 | |
| Total | 100 |
Strong submissions:
- show high project readiness, such as a confirmed site, technology partners, feedstock or offtake agreements, financing and permits
- present a credible business case
- include clear, traceable GHG calculations showing reductions that begin by 2031
- address every evaluation criterion clearly and completely
The Fund also aims to build a diverse portfolio across technologies and project sizes.
After You Submit
All applicants are notified once the EOI review is complete. Shortlisted applicants are invited to submit an FPP and give a presentation. Applicants who are not shortlisted can request a short feedback call.
Shortlisted applicants submit a detailed proposal of up to 40 pages, along with:
- a GHG quantification report and workbook
- a financial report and recent financial statements
- a detailed budget
- letters of financial commitment
- a readiness checklist
- a milestone summary table
Any material changes since the EOI must be identified and explained.
No. They are voluntary, kept confidential and not used in evaluation. The Fund asks that the person leading the project for the lead applicant complete them.